Prospector Avenue: Bonanza Drive to Sidewinder Drive

Print
Press Enter to show all options, press Tab go to next option
 pc logo  udot lgog

Información del proyecto se encuentra en español al hacer click aquí

 

Construction Update

September 7, 2018

Waterline installation on the south side and curb & gutter completion on the north side of Prospector Ave

Work will begin on the south side of the street on Monday, September 10. Crews will shift traffic – both vehicular and pedestrian – to the north side of the street.

One-way traffic will remain in the east-to-west direction

Initial activities include removal of the existing sidewalk, curb and gutter and light poles.

Driveways on the south side of the street may be narrowed to half, but access will remain open during construction.

Drainage/waterline work continues across Prospector Ave, across from Lot K. This activity is sometimes stop-controlled and flagger operated.

The pedestrian ramp on the south side of intersection with Bonanza Drive is scheduled to be removed on Monday, September 10 and reconstructed over the 2 – 3 days following. Pedestrians and cyclists should begin to use the north side of the street for access to and from Prospector Ave.

Note: For the safety of motorists, pedestrians, and the various construction crews in the area, the speed limit has been reduced to 25 mph on Prospector Avenue. Please be mindful of your surroundings and proceed through the corridor with caution and awareness.

Park City Police will be patrolling the area to enforce the one-way traffic operations. Violators will be fined.

Reminder:

Prospector Avenue traffic will be open to one-way travel only, heading westbound.
Prospector Ave can be accessed from Sidewinder and Poison Creek, but vehicles will not be able to enter Prospector Ave from Bonanza. This configuration will be in place through the full length of the project. A map below provides detail regarding the direction of travel during construction. 

Prospector Square Update:

The Prospector Square Property Owner’s Association is making improvements to Lots D and H. This work is being performed and managed by separate contractors and entities from the Prospector Avenue improvements, however, representatives from both projects are in close coordination with one another. Current activities include:

Beginning Thursday, Aug. 30, work will resume in Lot H (Good Karma) with additional concrete forms followed by the pouring of concrete over the next few days. In addition, we hope some work will commence next to the New Claim Condos in Lot D. Paving in Lot H is expected to begin in the next two to three weeks. The contractor must let the entrance concrete cure before their heavy trucks bring asphalt into the lot. The project is behind schedule, overall, due to multiple factors but all sewer work will be completed early next week. With the exception of landscaping, work in Lot H will by substantially complete by the end of September.

One side benefit in Lot H was completed this week — Cache Valley Electric laid fiber optic cable for All West Communications.

Final landscaping curbing is complete near Picabo Academy. A major concrete failure was also fixed in the Lot D garage earlier this week. 

There will be no work done on Saturday, Sunday and Monday due to the Labor Day holiday. Work will recommence on Tuesday.

If you have any concerns you want addressed, please contact:

Craig Dennis
Executive Director
PSPOA
e: craig@dennis.net 
p: 801.368.4303

Project Overview

Park City Municipal Corporation in coordination with the Utah Department of Transportation is improving Prospector Avenue between Bonanza Drive and Sidewinder Drive. The project will enhance and promote alternative multi-modal transportation uses and address roadway infrastructure needs by:  
  • Creating a safe environment for all modes of travel
  • Reducing vehicular speeds by introducing a "complete street" cross section
  • Defining more efficient use of existing space by better marking travel lanes and bus pullouts
  • Upgrading the street lighting with LED fixtures
  • Improving the roadway drainage
  • Resurfacing the asphalt pavement

The project team is working closely with the Prospector Square Property Owners Association to coordinate with their recently completed Master Plan.  

Public Outreach

A copy of the Meet the Contractor Open House flyer is available below.  The meeting was held on June 28, 2018 from 5:30 - 7:00 pm at the Park City Marriott to introduce the contractor to the community.  The presentation boards are available at the following links. 

MEET THE CONTRACTOR OPEN HOUSE PRESENTATION - JUNE 2018

Meet the Contractor Boards_Page_01

Park City hosted an open house on Tuesday, November 29th, 2016 to provide an opportunity for the public to learn more about the improvements along Prospector Avenue between Bonanza Drive and Sidewinder Drive. The information boards and the project map presented at the meeting available at the following links:

PRESENTATION BOARDS

Public Meeting #1 Presentation_FINAL_Page_1

PROJECT MAP

 2016-11-29 Public Open House Scroll Plot_final

 

 

prospector street 2 prospector street   prospector sidewalk 2
prospector sidewalk 1  prospector curb gutter lighting

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer